2008 Building the Winery
Here are architectural drawings of the winery. The pictures show the lower and upper level floor-plans and cross-sections.
1. Sep 29, 2007: Start of excavation
2. Nov 29, 2007: Framing the building floor
3. Dec 16, 2007: Flaming the cellar walls
4. Jan 22, 2008: Framing the upper floor
5. Feb 6, 2008: Framing the top
6. Apr 6, 2008: Framing the roof
7. Jul 8, 2008: Sealing the roof
8. Aug 28, 2008: Preparing the driveway
9. Sep 4, 2008: Planting the roof
10. Sep 4, 2008: All done!
Here is a time lapse sequence of pictures during the construction process